NEW QUESTION 154
Which is a minimum requirement for applying the organization theme?
- A. The roles of the project management team must be combined, wherever possible
- B. The project manager must be appointed from the supplier organization
- C. Each member of the project management team must have a written role description
- D. The frequency of communication to the project's stakeholders must be documented
Answer: D
Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Themes#Organization_Theme
NEW QUESTION 155
Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
- A. product
- B. quality
- C. risk
- D. supplier
Answer: D
NEW QUESTION 156
Which regular report provides the Project Board with a summary of stage status?
- A. Communication Management Strategy
- B. Checkpoint Report
- C. Highlight Report
- D. Project Brief
Answer: C
NEW QUESTION 157
Which describes the 'Identify Risks' step within the recommended risk management procedure?
- A. Identify responses to risks documented in the Business Case
- B. Gather information about the project environment and objectives
- C. Identify uncertainties that may impact on the delivery of the project objectives
- D. Identify the roles to be involved in risk management activities
Answer: C
NEW QUESTION 158
Which theme estimates the cost of delivering the project?
- A. PROGEESS
- B. Plans
- C. Business case
- D. Change
Answer: C
Explanation:
Explanation
Reference http://prince2.wiki/Business_Case
NEW QUESTION 159
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
- A. Risk Register
- B. Off-specifications
- C. Follow-on action recommendations
- D. Issue Register
Answer: C
Explanation:
Section: Volume A
NEW QUESTION 160
Which product records any project outcomes perceived as negative by stakeholders?
- A. Communication Management Strategy
- B. Project Product Description
- C. Project Plan
- D. Business Case
Answer: D
NEW QUESTION 161
Where should the names of those who are to approve a product be recorded?
- A. Configuration Item Record
- B. Checkpoint Report
- C. Product Status Account
- D. Product Description
Answer: D
NEW QUESTION 162
To meet the minimum requirements for applying the progress theme, what must be considered?
- A. How lessons will be learned
- B. Which management products will be baselined
- C. Who is responsible for reporting on progress
- D. How time-driven reports will be produced
Answer: D
Explanation:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Themes
NEW QUESTION 163
Which describes a project benefit?
- A. A specialist product of the project
- B. A measurable improvement resulting from an outcome
- C. An uncertain result caused by project actions
- D. The result of a change derived from using the project's products
Answer: B
NEW QUESTION 164
Which is a recommended quality review team role?
- A. Administrator
- B. Project Support
- C. Assurance
- D. Project Manager
Answer: A
NEW QUESTION 165
Which statement about the quality review technique is FALSE?
- A. It enables a check to be made on a product's fitness for purpose
- B. It defines the quality responsibilities of the project team
- C. It is used to gain wider acceptance of a product by involving key interested parties
- D. It supports the management of future changes by providing a baseline for a product
Answer: B
Explanation:
Section: Volume B
NEW QUESTION 166
Which is a benefit of using PRINCE2?
- A. Provides for the efficient and economic use of management time
- B. Is a method specifically designed for technical projects
- C. Can be used to manage both projects and programmes
- D. Includes many of the proven planning techniques, such as critical path analysis
Answer: A
NEW QUESTION 167
Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?
- A. Scope
- B. Risk
- C. Timescale
- D. Costs
Answer: A
NEW QUESTION 168
Why is it crucial that the Project Product Description clearly defines acceptance methods?
- A. Enables Project Assurance to authorize quality activities
- B. Provides confirmation that all project products have met their quality criteria
- C. Defines how all project products will be reviewed and approved
- D. Defines how it will be proven that the completed project product meets the customer's expectations
Answer: D
NEW QUESTION 169
......