NEW QUESTION 21
Which service determines the primary node after powering on the VxRail nodes during the deployment of a VxRail cluster?

  • A. Loudmouth
  • B. Election
  • C. Marvin
  • D. Mystic

Answer: C

 

NEW QUESTION 22
What is validated by running the Proactive Network Performance test in vCenter on a VxRail cluster?

  • A. Network configuration and performance for vSAN
  • B. Network performance for virtual machines
  • C. Latency measurement between DCs for Stretched Clusters
  • D. Latency and bandwidth measurement to the witness host

Answer: D

 

NEW QUESTION 23
Which VxRail model can only be installed with static rack rails?

  • A. G Series
  • B. S Series
  • C. V Series
  • D. P Series

Answer: C

 

NEW QUESTION 24
An implementation engineer is tasked with setting up RecoverPoint for VMs on a new 4-node E Series VxRail duster How many VMs are licensed to be protected on the cluster?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: B

 

NEW QUESTION 25
What environmental components of a 3-node VxRail cluster must be assigned IP addresses?

  • A. ESXi Mgmt, vCenter, Witness Traffic Separation, and iDRAC
  • B. vSAN, Witness Traffic Separation, vRealize Log Insight, and vMotion
  • C. vRealize Log Insight. vSAN, VxRail Manager, and SRS
  • D. ESXi Mgmt, vSAN, vMotion, and iDRAC

Answer: D

 

NEW QUESTION 26
An implementation engineer is performing a precheck on a VxRail cluster before expansion. During validation, they find out that the host is not compatible.
Use the VxRail simulator to describe why the host is Incompatible.
Note: It is necessary to close (x) the simulator window before you can select a response to this question.





  • A. Invalid vCenter 5erver license
  • B. Insufficient number of vSphere licenses
  • C. Firmware of ESXi host needs to be updated
  • D. bmc and bios are running older versions

Answer: A

 

NEW QUESTION 27
An implementation engineer is reviewing the customer requirements for a VxRail implementation The customer has specified noncontiguous hostnames and IP addresses What option should the engineer select in the VxRail Deployment Wizard to input the hostnames and IP addresses?

  • A. Custom
  • B. Autofill - with the correct incrementor
  • C. Advanced
  • D. Autofill - with the correct offset

Answer: D

 

NEW QUESTION 28
A VxRail E560F model was delivered six months ago and is now scheduled to be installed with the target code. What is the correct order of steps to complete this task?

Answer:

Explanation:

 

NEW QUESTION 29
What is a requirement for the vSAN Data-at-Rest Encryption?

  • A. All-Flash or AII-NVMe VxRail
  • B. External customer provided vCenter
  • C. External Key Management Server
  • D. VxRail with at least 3 nodes

Answer: C

 

NEW QUESTION 30
A VxRail Manager VM must be configured as follows:
* IP address: 192 168.10.16
* Net mask: 255.255.255.0
* Gateway: 192 168 10 254
Which command must be used?

  • A. vxrail-primary -config --vxrail-address 192.168.10 16 --vxrail-netmask 255 255 255 0 -vxrail-gateway 192.168,10 254
  • B. vxrail-network -config --vxrail-address 192.166 10 16 --vxrail-netmask 255 255.255 0 --vxrail-gateway 192.168.10.254
  • C. vxrail-prrmary -config --ip 192 168 10 16 -netmask 255 255 255 0 -gateway 192 168 10 254
  • D. vxrail-network-config --ip 192 168 10.16-netmask 255.255.255.0-gateway 192 168 10.254

Answer: A

 

NEW QUESTION 31
A VxRail Test Plan has been completed What is the protocol for recording the results'?

  • A. With the implementation team, complete each test and document the test date
  • B. With the implementation team, complete and document each test, test date, and a screenshot of results
  • C. In front of a customer, complete each test and document the test date
  • D. In front of a customer, complete and document each test, test date, and a screenshot of results

Answer: D

 

NEW QUESTION 32
An implementation engineer is tasked with setting up RecoverPoint for VMs on a new 4-node E Series VxRail duster How many VMs are licensed to be protected on the cluster?

  • A. 0
  • B. 1
  • C. 2
  • D. 3

Answer: D

 

NEW QUESTION 33
Which vSAN rules are configured for the VXRAIL-SYSTEM-STORAGE-PROFILE?

  • A. Failures to tolerate - 1 failure RAID-1 (Mirroring)
    Object space reservation - Thin provisioning
  • B. Failures to tolerate - 2 failures RAID-1 (Mirroring) Object space reservation - Thin provisioning
  • C. Failures to tolerate - 1 failure RAID-1 (Mirroring) Object space reservation - Thick provisioning
  • D. Failures to tolerate - 1 failure RAID-5 (Erasure Coding) Object space reservation - Thick provisioning

Answer: B

 

NEW QUESTION 34
An implementation engineer is deploying a new VxRail cluster What should they confirm before installing the hardware?

  • A. Power distribution supports only the power rating of a single node
  • B. Service laptop is on the same IP network as the iDRACs
  • C. At least 24 in (61 cm) of clearance exists in front of and behind the cabinet
  • D. Redundant power zones exist with adequate power cables

Answer: A

 

NEW QUESTION 35
A VxRail solution will be deployed with the embedded vCenter and an external DNS At a minimum, for which components must DNS records be created?

  • A. vCenter Server Platform Services Controller, and iDRAC
  • B. vCenter Server, ESXi hosts, and VxRail Manager
  • C. ESXi Hosts, VxRail Manager and iDRAC
  • D. vCenter Server Platform Services Controller, and VxRail Manager

Answer: B

 

NEW QUESTION 36
......

Authentic Best resources for DES-6322: https://www.testkingpdf.com/DES-6322-testking-pdf-torrent.html